May-June 2008

  • 1
  • 2

Peer-Reviewed Feature Clovis Landfill Reclamation Project

This landfill reclamation will pay for itself over time—and the project will also reap non-monetary benefits.

Article Tools

Create a Link to this Article

By Luke Serpa

Comments


All personnel working on the project have been trained regarding these potential hazards, and they regularly monitor for their presence. The operators of the bulldozer and the excavator monitor the waste they excavate for any visual or odorous indications of fuel, chemical wastes, friable asbestos, or other hazardous materials. Work is suspended if any suspicious materials are encountered until the materials are identified and removed in an appropriate manner. Work is also suspended if any significant amount of dust is produced and water is applied to the excavation area before resuming. The excavation face is monitored every two hours using a photoionization detector (PID) and an oxygen/lower explosive level (LEL) meter. Work is stopped if the PID shows that VOCs are present at levels greater than 5 ppm, or if the LEL meter detects methane at a concentration of more than 1% or the oxygen level is below 16%.

Fortunately, the Clovis Landfill has only accepted waste from within the city limits, and there are not any large industrial operations in the city that produce significant quantities of hazardous wastes. Almost all of the waste that is being excavated originated from residential or commercial sources, so the types and quantities of hazardous materials that have been encountered are limited to what is typical of household hazardous waste. Since the project’s inception, the VOCs have never exceeded 5 ppm, nor has the methane ever exceeded 1% or the oxygen concentration been below 16%. The material also has sufficient moisture content to prevent the generation of significant dust. Periodically, a smoldering fire has developed due to the spontaneous combustion of waste that has recently been uncovered, but these have been easily addressed by using the bulldozer to spread the material and a water truck to extinguish the fire.

When the regulatory agencies set conditions for the project, they did not require that the excavation face be covered at the end of each day. Currently, the open excavation face measures approximately 12 acres. It is notable that the open excavation of this landfill has not led to significant nuisances, probably due to the climate. The area receives approximately 12 inches of rain per year, almost all of which occurs during the colder winter months, and the summers are hot and dry. When the material’s moisture content is conducive to nuisances and vectors, it is too cold, and when the temperature is conducive, it is too dry.

Odors are noticeable immediately adjacent to the excavation, but they are not severe and do not usually migrate very far. Birds are not a significant problem at the facility, and any that are present tend to congregate on the active face of the landfill and not on the excavation face. Other vectors, such as flies and small mammals, also appear to be much less attracted to the excavation face than they are to the active face where the new trash is placed. Litter is periodically blown from the excavation face, but the quantity is easily collected by the one person assigned to the task except during periods of very high winds.

Costs Versus Benefits
The feasibility study identified the benefits of the project to be the ability to reutilize and expand the landfill to serve the city for a much longer period of time, the mitigation of the groundwater contamination, and the recovery of soil, which eliminates the need to import soil for ongoing operations. The study quantified the value of these benefits and found that they exceeded the estimated cost of the project. As the project is nearing completion, it is possible to re-evaluate the project based on the actual results and costs.

We find that the project has in fact achieved the goals for expansion, groundwater mitigation and soil production. At the end of 2006, the city received a new solid waste facility permit that provides for the expansion of the facility through the redevelopment of the old unlined portion of the facility. The city will realize almost 30 years of additional lifespan at the facility by reconstructing this area and operating it as a modern landfill. The VOC levels in the underlying groundwater have steadily decreased as the project has progressed, and projections show that the contamination will continue to attenuate, thereby eliminating the need for the city to perform costly remediation. Finally, the soil that has been recovered from the project, which equals approximately one-third of the material that has been excavated, is adequate to meet the facility’s operational needs for more than 20 years.

Unfortunately, we also find that the project has cost substantially more than was estimated in the feasibility study. In 1998, the project was expected to cost $3.8 million, whereas the actual cost of the project is going to be approximately $9 million. This increase in the cost is primarily the result of two factors; the quantity of waste to be excavated was underestimated and the daily productivity was overestimated.

The estimate for the quantity of in-place waste was based on operating records and exploratory drilling, and was originally 1.9 million cubic yards. In reality, the bottom surface of the waste differed significantly from the estimate, and the actual quantity of material that will be excavated and sorted is 2.5 million cubic yards, 32% more than the original estimate.

The feasibility study also estimated the daily productivity at 4,500 cubic yards, whereas the actual productivity only averages 1,300 cubic yards per day. This discrepancy has greatly increased both the time to complete the project and the overall cost.

Re-evaluation of the project using these actual costs shows that the project is just above the “break-even” point; the projected value of the benefits is only slightly higher than the actual cost. However, even this comparison is based on assumptions of future conditions and costs that could change significantly. If future regulations to control greenhouse gas emissions or energy prices were to make waste-to-energy more feasible during the next 40 years, it could render the expanded capacity at the Clovis Landfill unnecessary thereby reducing the value of that benefit.

On the other hand, it is just as likely that future deviations from the assumptions will actually improve the cost-benefit ratio. For example, one of the surprising findings of this project was how slowly the buried waste was decomposing in the landfill; partially burned newspapers from the 1950s were still readable.

Advertisement

It may become beneficial some day to implement a process to accelerate the decomposition of this waste, such as a bioreactor landfill, in order to greatly shorten the post-closure monitoring period. Having all of the waste on a liner with a leachate collection and removal system may make such a process much more feasible.

One of the challenges of managing any capital improvement like a landfill is the need to make sound decisions that are based on long-term assumptions and projections about the future. The actual cost of a project may be significantly different than the estimate, and the actual value of the project may not be known or realized for years, or even decades. Clovis’ landfill reclamation project has been a relatively long and costly endeavor that is expected to pay for itself over time, but the project will also reap non-monetary benefits. The value of public perception, environmental responsibility, and peace of mind are not easily quantified. Regardless of what the future holds, it is doubtful that 40 years from now anyone that has been involved with this project will look back and regret the decision to move all of the waste at this landfill onto a liner.

  • 1
  • 2

What Do You Think?

Post a Comment

Be the first to tell us what you think!

Post a Comment

Not a subscriber? Sign Up
 
 
*  
 




 

Get MSW Email Updates!

Get weekly news and updates through our MSW email newsletter!