|


Prevention
is the best approach to landfill fires, but when that
fails, you better be prepared with a timely and effective
response.
By
Paul Henderson and Tony Sperling
Background
Why the Fire Started
Fighting the Fire
Monitoring Program
Conclusions and
Lessons Learned
References
Small surface
fires at MSW landfills are relatively common as a result
of the presence of potentially flammable materials and
such ignition sources as hot vehicle exhausts, improperly
disposed of cigarette butts, and loads that inadvertently
contain smoldering materials (Ettala et al. [1996] report
285 surface fires in Finlands 633 sanitary landfills
each year). These fires can generally be quickly suppressed
through the use of water or cover material or the removal
of the burning material from the active landfill area.
Underground fires are a much greater threat because
it is often difficult to determine the extent of the
fire, and suppression using conventional means is often
ineffective.
On October
18, 2000, City of Vancouver, BC, staff discovered an
underground fire in an area of the Vancouver Landfill
filled with woodwaste demolition material. Although
the area obviously affected by the fire was only about
50 m2, the total volume of demolition
material in the area in question was approximately 300,000
m3. A fire in a private demolition landfill
located near the Vancouver Landfill involving approximately
250,000 m3 of demolition material in the
fall of 1999 cost approximately $4 million to extinguish
over a period of four months.
Given the
potential impacts of a large underground fire, it was
critical to ensure that the Vancouver Landfill fire
was brought under control as quickly as possible and
that any risk of future fire was minimized.
Background
The Vancouver
Landfill is located at the southwest corner of Burns
Bog in the municipality of Delta, approximately 20 km
south of Vancouver. The facility is owned and operated
by the City of Vancouver and receives approximately
400,000 metric tonnes of MSW each year.
Demolition
materials consisting primarily of woodwaste from the
demolition of wood-frame buildings are accepted at the
Vancouver Landfill for use in the construction of a
"mattress layer" under MSW. The mattress layer
provides a foundation layer on top of the compressible
peat established in the vicinity of the Vancouver Landfill.
The demolition material also acts as a conduit for drainage
of leachate from within the landfill to a perimeter
leachate-collection ditch.
The demolition
layer has been traditionally filled to a thickness of
approximately 3 m prior to filling with MSW. The area
where the fire occurred was previously an open ditch
system between two adjacent landfill cells. As part
of a strategy to increase the height of the landfill,
the demolition layer in this area was filled in two
lifts to create a drainage layer approximately 8 m thick.
A thicker drainage layer was installed to account for
future differential settlement of the underlying peat
soils. Demolition materials were installed in the area
over approximately three months commencing in the spring
of 2000. As shown in Figure 1, the total area that received
two layers of demolition material was approximately
80 x 700 m.
 |
| Figure
1. Landfill Area Receiving Demolition Material.
Click here
for enlarged views |
Why
the Fire Started
Spontaneous
combustion is the outbreak of fire without application
of heat from an external source. Spontaneous combustion
can occur through the storage of organic materials,
such as woodwaste, coal, tire chips, compost, or hay.
In organic
materials, spontaneous combustion occurs when heat initially
produced through biological degradation is not allowed
to dissipate, thus raising the temperature of the material.
Biological degradation will generally cause temperatures
to increase to approximately 70° C. At temperatures
much higher than 70° C, microorganisms die. Temperatures
beyond 70° C are associated with the chemical oxidation
of organic materials in the presence of oxygen. For
wood, exothermic oxidation commences around 200°
C and combustion with open flame commences around 300°
C (National Fire Protection Association, 1976). The
following table is a practical reference summary for
evaluating landfill fire temperatures based on our experience
with six major landfill-fire projects.
| Table
1. Landfill Temperature Characteristics |
|
<60°
C
|
Anaerobic
decomposition
|
|
<75°
C
|
Aerobic
decomposition
|
|
80°
C
|
Microbes
die off
|
|
93°
C
|
Pyrolysis
starts
|
|
149°
C
|
Exothermic
oxidation of wood starts
|
|
315°
C
|
Wood
ignites spontaneously (combustion)
|
For spontaneous
combustion to occur, conditions must be ideal. The following
conditions can lead to spontaneous combustion:
- a pile
of sufficient size to retain heat (the Ontario Fire
Marshals office recommends that woodchips be
stored in piles less than 4 m high and 8 m wide with
an overall volume of less than 1,000 m3
to avoid spontaneous combustion [Government of Ontario,
1998]),
- moisture
content around 25% on a wet basis (Legislative Assembly
of Ontario, 1998) (drier conditions prevent biological
activity, wetter conditions reduce porosity and prevent
temperatures from increasing beyond biological levels),
- supply
of oxygen (many spontaneous-combustion fires occur
near the windward edge of a pile of material during
windy conditions),
- sufficient
insulating capabilities to retain heat in the pile
(Swedish researchers found that uncovered, loosely
packed piles of demolition material piled up to 5
m high did not spontaneously combust, whereas compacted
piles regularly spontaneously ignited [Hogland et
al., 1996]),
- prolonged
storage of organic materials (the Ontario Fire Marshals
office recommends storage of woodchips for less than
three months [Government of Ontario, 1998]).
In the case
of Vancouver Landfill, the fire occurred behind an approximately
3-m-high bank of demolition material adjacent to an
internal site-access road. The road was located on top
of the first layer of demolition material, and the bank
represented the edge of the second layer of demolition
material. The bank had been partially covered with soil,
but sufficient void space was present to allow wind
to blow into the bank. The bank was located on the windward
side of the demolition lift. Material in the area of
the fire had been in place approximately six months.
 |
| Partially
capped bank on edge of demolition cell |
Fighting
the Fire
The fire
was discovered at approximately 2:00 p.m. on October
18. Although no flames were visible when the fire was
discovered, an area of approximately 50 m2
had settled approximately 60 cm, and smoke was venting
from it. Steam vents were previously noted throughout
the 700- x 80-m demolition area. With the discovery
of the fire, there was concern that the steam vents
indicated fires were also present in other areas of
the demolition cell since various authors have reported
that landfill fires may exist without showing any external
evidence (Ettala et al., 1996; Carpenter, 1996; and
Herold, 1999).
Within two
hours of the discovery of the fire, Poschner Construction
(the citys onsite contractor) was delivering water
to the fire in three off-road dump trucks with delivery
capabilities of 20,000 lit. per load. The trucks are
normally used at the landfill to deliver cover material.
In the event of a fire, the trucks can be quickly outfitted
with a tailgate to allow them to haul water. Water is
supplied to the trucks via an overhead delivery system
feeding from an onsite dredge pond. The trucks can be
filled in about three minutes.
Because the
demolition material is essentially free-draining and
the surface area where the fire was located was essentially
flat, large quantities of water could be applied without
reducing trafficability in the area or creating a risk
of slope failure. By the end of the evening of October
18, approximately 800,000 lit. of water had been delivered
to the fire area.
Off-road
dump trucks continued to deliver water to the area of
the fire and other hot spots within the demolition area
on October 19 and 20. By the end of October 20, the
water trucks had delivered a total of more than 2 million
lit. of water.
 |
| Poschner
Construction off-road truck, 20,000 lit. per load |
While the
off-road dump trucks were delivering water to the fire,
a pumping system was erected approximately 2,000 m from
the onsite dredge pond for conveying larger volumes
of water. The system involved pumping water from the
dredge pond into leachate collection ditches. The flooded
ditches were used to convey the water to the vicinity
of the fire. A 500-m-long pipeline was established to
convey the water into a large spray-irrigation cannon.
The spray-irrigation cannon was capable of delivering
approximately 14,000 lit. of water per hour and operated
continuously for a week commencing on October 20.
To prevent
air from entering the demolition layer, a cap of silty
clay from the dredge pond was installed along the 700-m-long
bank of the demolition area (see photo 3).
 |
| Clay
cover used to eliminate oxygen entry into landfill |
A case study
described by Hogland et al. (1996) shows a very similar
scenario to the Vancouver Landfill fire. In a controlled
experiment to monitor self-heating, Hogland et al. constructed
a 3.5- to 4-m-high pile of demolition material over
a 400-m2 area. The pile was compacted during
construction and covered with woodchips. Hogland et
al. monitored a variety of parameters for several months.
Temperatures of around 85° C were attained after
about two months. Almost no methane was recorded after
two months. Oxygen levels varied as a function of the
depth of the pile, but they were around 20% in the middle
and upper areas of the pile. A fire occurred after about
six and a half months of storage. The fire occurred
on the windward side of the pile the day after a strong
wind fully oxygenated the pile. In a single day, temperatures
in the pile increased from 85° C to approximately
240° C. To extinguish the fire, Hogland et al.
capped the pile with clay. After about two months, temperatures
in the pile dropped from several hundred degrees to
50° C.
Similarly,
fire erupted at the surface in a recent fire incident
within a 2 millionm3 demolition material
cell in Minnesota. After several days of digging, it
became apparent that the fire could not be contained
by excavation. Instead, the hot area was covered with
low-permeability soil, and water was injected into boreholes
drilled into the waste. After several weeks of monitoring
temperatures and gas compositions, it appears that the
fire abated and temperatures are returning to normal
levels.
In the Vancouver
Landfill fire, the Minnesota landfill case history,
and the fire described by Hogland et al., excavation
was not chosen as the preferred method to extinguish
the fire. It is difficult to determine the extent of
an underground fire, and the risk of excavating is that
additional oxygen will be delivered to the fire. To
minimize oxygen intrusion, any excavations to dig out
burning material or install fireguards should be immediately
backfilled with soil or other inert material.
Monitoring
Program
 |
| Figure
2. Carbon Monoxide Concentration Measurements, Vancouver
Landfill Fire. Click
here for enlarged view |
On October
20, the City of Vancouver retained Sperling Hansen Associates
Inc. to monitor the progress of the firefight and to
provide recommendations on future actions. Through a
simple monitoring program focusing on the installation
of subsurface probes in the demolition area, Sperling
Hansen was able to show conclusively that the fire had
been completely extinguished and that the conditions
that had created the potential for a fire had been resolved.
The monitoring
program involved collecting temperature and gas-composition
data throughout the demolition cell. Readings were taken
at all observed steam vents as well as over a grid of
regularly spaced "barhole punch" probes installed
through the intermediate cover into the shallow subsurface.
Barhole-punch
monitoring points were created by driving a solid-steel
bar approximately 1.5 m below grade with an excavator,
then pushing a hollow-steel, 2.5-cm-diameter sampling
pipe into the cavity. An oversize bolt was used to prevent
the pipe annulus from clogging during insertion. On
achieving full depth, the sampling pipe was pulled back
approximately 15 cm, dislodging the bolt and allowing
subsurface samples of gas composition to be collected.
Maximum temperatures
noted at the surface using a hand-held infrared sensor
were 54.1° C. On this project, as well as on several
other landfill fire projects investigated by Sperling
Hansen, temperature readings taken at the surface did
not prove to be particularly useful in indicating the
extent of the fire zone. Subsurface temperature readings
from thermistor strings installed in boreholes within
the waste typically provide a much more effective indication
of fire conditions in the subsurface. On this project,
thermistors were not installed because of the relatively
shallow fill and also on the basis that the gas composition
data from the barhole-punch monitoring program indicated
that the extent of the fire was limited. Gas samples
were analyzed using portable sensors for oxygen, methane,
carbon monoxide, and hydrogen sulfide.
At the start
of the monitoring program, subsurface oxygen levels
within the burn area were typically in the range of
15-21% oxygen. As firefighting and capping efforts progressed,
oxygen levels dropped consistently. By the time the
monitoring program was completed on November 3, oxygen
levels in most wells had dropped below 1%.
Similarly,
subsurface methane concentrations were below 1% methane
in many of the sampling ports at the onset of monitoring.
Low methane concentrations indicated that decomposition
was occurring in an aerobic regime. As mentioned previously,
aerobic decomposition is associated with greater generation
of heat and can lead to spontaneous combustion. By November
3, methane concentrations had climbed above 40% in most
of the wells.
On this project,
carbon monoxide (CO) proved to be the most effective
indicator of landfill fire. Initially, CO concentrations
up to 315 ppm were noted in the vicinity of the active
burn zone. These concentrations gradually declined as
the fire was brought under control. Because elevated
CO concentrations were not noted in steam vents and
barhole-punch sites outside the active burn zone and
because there was a direct relationship between CO concentrations
and fire activity, we believe that CO provides an excellent
indication of subsurface fire activity. Contours showing
the gradual reductions in CO concentrations are shown
in Figure 2.
Based on
observations on this project as well as on experience
at landfill fires at Campbell Mountain Landfill, the
Delta Shake and Shingle Landfill, and the recent landfill
fire in Minnesota, Sperling Hansen has developed the
following empirical scale that we now use routinely
to assess fire conditions in construction demolition
landfills.
| Table
2. Carbon Monoxide Concentrations |
| |
CO
(ppm)
|
|
No
fire indication
|
0-25
|
|
Possible
fire in area
|
25-100
|
|
Potential
smoldering nearby
|
100-500
|
|
Fire
or exothermic reaction likely
|
500-1,000
|
|
Fire
in area
|
1,000
|
Conclusions
and Lessons Learned
Based on
the experience developed from the Vancouver Landfill
fire, a number of conclusions can be reached with respect
to prevention of fires in demolition materials and effective
fire control methods:
Fire
Prevention. Intermediate cover material must
be installed on all exposed slopes with particular attention
given to windward slopes; fill plans incorporating vertical
firebreaks need to be developed for demolition areas
to limit the potential extent of any fires; and because
of their composition and porosity, woodwaste demolition
materials pose an extreme fire risk and must be handled
with equal or more caution than MSW.
Firefighting
and Monitoring. Sufficient equipment resources
and personnel must be available to immediately respond
to any landfill fire; the approach of cooling down an
underground fire with large volumes of water proved
effective in this situation and is expected to work
equally well on other demolition-material fires, provided
the hot zone is shallow (10 m); cutting off the oxygen
supply to the burn zone is an effective way to fight
fire in demolition materials; an effective monitoring
program is essential in determining the extent of an
underground fire and to monitor progress in fighting
the fire; subsurface carbon dioxide levels in conjunction
with methane and oxygen levels provide critical data
in determining the extent of a fire and evaluating the
potential for a fire to develop; and to reduce the risk
of spontaneous combustion, operators should strive to
establish anaerobic conditions within demolition landfills
whereby oxygen is totally excluded, with methane and
carbon dioxide being the predominant gases.
References
Carpenter,
M. "Subsurface Refuse Fires, Evolution and Control:
Case Study at Palailai Landfill, Oahu, Hawaii."
SWANA 1999 Northwest Regional Symposium, pp.
385-398. 1996.
Ettala,
M. et al. "Landfill Fires in Finland." Waste
Management and Research, pp. 377-384. 1996.
Herold,
G. "Subsurface Landfill Fire Suppression and Monitoring."
SWANA 1999 Northwest Regional Symposium. 1999.
Hogland
W., T. Bramryd, and I. Persson. "Physical, Biological
and Chemical Effects of Unsorted Fractions of Industrial
Solid Waste in Waste Fuel Storage." Waste Management
and Research, pp. 197-210. 1996.
National
Fire Protection Association. Fire Protection Handbook,
Fourteenth Edition. Boston, MA. 1976.
Paul Henderson,
P.E., is manager for the City of Vancouver Landfill.
Tony Sperling, P.E., is president of Sperling Hansen
Associates in North Vancouver, BC.
|