|


Natural
disasterswhether they are hurricanes, fires, earthquakes,
tornadoes, floods, or other occurrencescreate
unique waste management challenges.
By
Tammy L. Hayes
No matter
where in the country you are, some form of natural disaster
can devastate your community. With all of the other
things there are to worry about when a natural disaster
strikes, such as public safety and infrastructure concerns,
you also have to remove the remaining refuse. Experience
has shown that managing the enormous amounts of debris
in the aftermath of a disaster is most effectively accomplished
through emergency-preparedness planning. Are you ready?
Do you know
whom to call when the dust settlesall over everything?
Do you have pre-event contracts in place to manage the
debris? Do you have sites designated to sort everything
out? Do you know what costs can be reimbursed? Do you
know what the Federal Emergency Management Agency (FEMA)
requirements are for you to get those costs reimbursed?
This article will show you what some communities have
experienced and what you can do to be prepared.
Hurricane
Opal
In October
1995, Hurricane Opal swept through the Panama City area
in Florida's panhandle, creating more than 65,000 tons
of construction-and-demolition debris, uprooted trees,
and other vegetative waste in the unincorporated areas
of the county alone. Almost immediately, Bay County
received approximately 60 unsolicited responses from
contractors and debris removal firms. The county decided
to take an aggressive restoration approach.
A two-phase
program was developed for the management of emergency
cleanup activities. The first phase produced a plan
for the cleanup (since one was not in place), and the
second phase involved implementing the plan. First,
responses from the contractors were consolidated, qualifications
statements were developed for interested firms, bidders
were prequalified, and bid proposals were receivedall
within three and a half days. A favorable contract price
was then negotiated for loading, hauling, and disposing
of the storm debris.
The implementation
phase included monitoring load, collection, and hauling
contractors; monitoring landfill scales and weight tickets;
and providing daily reports on more than 200 loads per
day that were disposed of at the county landfill. A
public information and hotline system was also set up
to answer inquiries from local residents. Cleanup activities
were closely coordinated with FEMA and the Florida Department
of Community Affairs to meet strict guidelines for cost
reimbursement. Many meetings were held to discuss required
documentation and the eligibility of a negotiated fee
for contractors instead of a bid.
A team of
12 people worked full-time to manage this cleanup, and
its success was the result of a dedicated, talented
staff. However, emergency planning could have expedited
the process.
Hurricane
Irene
In October
1999, Hurricane Irene struck southern Florida with winds
up to 95 miles per hour and rainfall up to 15 inches,
leaving an extensive cleanup effort for Palm Beach County.
The Solid Waste Authority of Palm Beach County (SWA)
was called upon to lead the emergency response and storm-debris
cleanup program. Overwhelmed with the amount of debris
and the realization that the cleanup effort would cost
both time and money, SWA contacted CDM to assist in
monitoring waste collection and obtaining reimbursement
funds from FEMA.
Within 72
hours, personnel were mobilized from around Florida
and positioned at eight sites to monitor the hauling
contractors and document the quantity, quality, and
origin of the waste. Once the governor declared a state
of emergency, the Florida Department of Environmental
Protection (FDEP) issued an emergency final order, which
authorized the open burning of hurricane-generated yard
trash and demolition debris by local governments or
their agents in remote locations, as well as in air-curtain
incinerators anywhere in the emergency area.
Sites were
initially identified as potential debris management
sites. SWA management personnel coordinated closely
with the cities, contract haulers, various county departments,
and other agencies to ensure that storm debris was collected
quickly and efficiently and processed or disposed of
properly. Six emergency vegetative-debris-handling sites
were opened from 7:00 a.m. to 7:00 p.m. seven days a
week. SWA conducted daily conference calls with all
cities and the county emergency operations center to
ensure that they were being responsive to the needs
of the cities and the haulers.
The hurricane
generated approximately 250,000 cubic yards of debris;
the majority was vegetative waste that was mulched.
About half of the mulch was either open-burned or used
as fuel in a nearby cogeneration plant. The other half
was either used by the county or left on existing closed
landfills. None of it was landfilled. Because careful
records were kept, SWA recovered approximately $3 million
of the total $3.3 million spent on the clean-up efforts
from FEMA.
Marc Bruner,
director of planning and environmental management for
SWA, comments that "Hurricane Irene was the last storm
we were unprepared for. At that time we had no pre-event
contracts in place and no real debris management plan."
He goes on to say, "That year was a wake-up call for
Palm Beach County because Hurricane Floyd, which was
a major [Category 4] storm, just missed us and Hurricane
Irene hit us, although that was a minimal hurricane
[Category 1 at the time it hit Florida]. Now we are
prepared for any future storm events."
Fires
in New Mexico
In May 2000,
Los Alamos County residents were devastated by the Cerro
Grande wildfire, which burned more than 47,000 acres
and destroyed more than 400 residences and other structures.
Although the county had excellent safety and evacuation
procedures in placeno lives were lost, and no
civilians were injuredthere was no plan for the
removal of more than 162,000 cubic yards of debris that
remained as a result of the fire's destruction.
The steps
taken to accomplish this feat entailed assessing the
damage, identifying FEMA guidelines, estimating the
volume of material, and evaluating disposal and recycling
alternatives. One of the obstacles that had to be overcome
was that the local landfill was closing and had limited
capacity, with the nearest landfill being 150 miles
away. Another was that household hazardous waste and
asbestos-containing material (ACM) had to be isolated
and removed, and there are only three landfills in New
Mexico that accept ACM.
Approximately
95% of the debris was ultimately either reused or recycled.
Foundations, stem walls, and retaining walls were excavated
and crushed to 1.5-inch material, which was stockpiled
for use on county road projects. Burned trees and other
vegetation were chipped and delivered to a local golf
course under construction, and metal was delivered to
local scrap yards. All debris removal and reconstruction
efforts had to be coordinated with the County, the New
Mexico Environment Department (NMED), the State of New
Mexico, FEMA, and the Los Alamos National Laboratory.
The people
who worked on this project suggested that anyone who
goes through this put together "lessons learned" when
the work is completed and revise the plan accordingly.
The lessons learned from this experience included the
following:
- Prepare
a disaster-debris management plan. Identify chipping/grinding/disposal
sites and include a hazardous mitigation plan.
- Preselect
a contractor for on-call services.
- Know FEMA's
guidelines for reimbursement.
- Keep accurate
data.
- Establish
a "hotline" for homeowners.
- Update
the plan on a regular basis.
- Identify
chipping/crushing/burning sites.
- Prepare
an oversight/tracking plan.
- Plan for
the worst and hope for the best.
- Be ready
to work long hours.
FEMA
Requirements
Understanding
FEMA requirements prior to an emergency enables you
to recover the maximum amount of cleanup costs allowed.
FEMA's Public Assistance Program, set up under the authority
of the Robert T. Stafford Disaster Relief and Emergency
Assistance Act, provides supplemental federal disaster
grant assistance for the removal of debris, the implementation
of emergency protective measures, and the permanent
restoration of public infrastructure. This program is
based on a partnership of FEMA, state, and local officials,
so close coordination among all of these agencies is
important. Details can be found on FEMA's Web site (www.fema.gov)
,but the basic elements of this program are described
below.
The state
plays the role of "grantee" and is responsible for administering
the federal grant, so you need to know your state's
emergency management agency and whom to contact there
(this information can be found on FEMA's Web site).
To begin the process, you must submit a Request for
Public Assistance form to the state (also found on FEMA's
Web site). You can do this at a state-sponsored applicants'
briefing, at which you will receive information about
the Public Assistance Program and state requirements.
Eligible
applicants include states, local governments, Indian
tribes, and certain private non-profit organizations.
The federal share of assistance is not less than 75%
of the eligible cost for emergency measures and permanent
restoration. The state determines how the non-federal
share (up to 25%) is split with the applicants.
To be eligible,
the work must be required as the result of the disaster,
be located within the designated disaster area, and
be the legal responsibility of an eligible applicant.
Work that is eligible for supplemental federal disaster
grant assistance is classified as either emergency
or permanent work.
Emergency
work includes debris removal from public roads and rights
of way, and emergency protective measures performed
to eliminate or reduce immediate threats to the public.
Permanent work includes work to restore an eligible
damaged facility to its pre-disaster design for categories
such as roads and bridges, water control facilities,
buildings, utility distribution systems, and public
parks and recreation facilities.
FEMA accepts
the following four methods of procurement under the
conditions delineated below:
- Small
purchase procedures can be used for items that
cost less than $100,000. Several price quotes are
required, but publicly advertised bidding is not.
- Sealed
bids must be publicly advertised, with
a contract awarded to the responsive bidder with the
lowest cost.
- Competitive
proposals are used for procuring architectural
or engineering professional services, and contracts
are awarded based on qualifications.
- Noncompetitive
proposals are accepted when an item is available
from only one source, an emergency requirement will
not permit delay, FEMA authorizes noncompetitive proposals,
or solicitation from multiple sources was attempted
but the competition was inadequate.
Additionally,
one of the following contract types must be used:
- Lump
sum contracts can be used where a clearly
defined scope and price are possible.
- Unit
price contracts can be used when the work
can be broken into items and a cost per unit determined.
- Cost
plus fixed fee is either a lump sum contract or
a unit price contract with a fixed contractor fee
added.
- Time
and materials can be used only for the first 70
hours following a disaster when a clear scope cannot
be developed. They must include a "not to exceed"
provision.
For some
services, pre-event contracting can be an acceptable
way of arranging a reputable, qualified contractor on
a standby basis for performing certain types of repair
or replacement work. Pre-event contracts are most commonly
used for disaster-debris cleanup since the scope of
work is relatively well-defined. Pre-event contracts
covering disaster-debris cleanup can be bid as both
time and materials contracts to account for the immediate
cleanup following the first 70 hours, and unit price
contracts that generally prescribe payment on a volume
(dollar-per-cubic-yard) or weight (dollar-per-ton) basis
of debris collected, hauled, reduced, and/or disposed.
The key
to cost reimbursement is documentation, documentation,
documentation.
Disaster
Debris Management Planning in South Carolina
In recent
years, both hurricanes and floods have left their marks
on the Carolinas. In the aftermath of these events,
public utilities are stretched to their limits and need
to rely on outside contractors to assist with repair
and cleanup efforts. Some communities that have suffered
during past disasters have expressed frustration with
procuring qualified, reputable contractors. Recognizing
these problems, the Berkeley County Water & Sanitation
Authority (BCW&SA) understood that planning before
a disaster hit was important for an effective and timely
debris cleanup operation. They prepared a debris management
plan that outlines responsibilities and tasks, identifies
debris clearing priorities, classifies debris, provides
guidance for operating debris reduction and storage
sites, and specifies waste segregation procedures. To
enhance the level of preparedness in the event of a
disaster, BCW&SA has also put in place a pre-event
or standby contract.
To initiate
its pre-event contracting effort, BCW&SA developed
a comprehensive Request for Proposals (RFP). The RFP
solicited qualifications, experience, and price with
respect to the tasks above. Six firms responded to the
RFP, and the list was narrowed down to a few of the
most qualified firms. Following interviews, one firm
was selected that was capable of providing the entire
scope of services. A five-year standby contract was
signed, which can be renewed or cancelled at the end
of each year. The contract includes plans and specifications
detailing how the debris is to be collected, hauled,
reduced, and disposed of. Language is included to document
requirements for such items as a temporary debris storage
and reduction site (TDSR) set-up and restoration, traffic
safety, and filling in holes from uprooted trees.
The following
tasks are included in Berkeley County's pre-event contract
based on FEMA guidelines:
- Initial
debris clearing following the first 70 hours after
the disaster. This part of the contract is set
up as a time and materials contract. The only work
reimbursable for this part of the contract is moving
debris from the major roadways to allow emergency
access to affected areas.
- Debris
collection, hauling, reduction, and disposal.
This part of the contract is set up as a unit price
contract. Payment is based on the cubic yards of material
collected, delivered to one of several pre-identified
TDSRs, reduced at the TDSR, and hauled to a final
disposal site.
- Clearing
of sewer easements. This part of the contract
is also set up as a unit price contract. Payment is
based on the cubic yards of material cleared from
sewer easements.
- Provision
of food, water, and shelter for essential county employees
and their families. This task was included so
that BCW&SA employees essential to disaster response
would be available for critical infrastructure repair,
should their own homes be damaged.
They also
retained a consulting engineering firm to monitor all
debris contractor operations; track and report on debris
management progress; provide public relations assistance;
provide hazardous-waste-material specialists; provide
engineering services related to the inspection, design,
and repair of critical infrastructure; provide annual
training and coordination for county employees; and
assist with debris management planning. According to
Marc Hehn, director of BCW&SA, "Having this plan
in place is of great benefit to Berkeley County. Having
worked here for 20 years, I well remember Hurricane
Hugo, and I feel very good that we can call upon CDM
to help manage our contractor in the removal of debris,
restoration of water and sewer service, and FEMA requirements."
Preparedness
in Massachusetts
On a broader
scale, the Massachusetts Emergency Management Agency
(MEMA) recently revised its existing Disaster Debris
Management Plan. This plan details FEMA Public Assistance
eligibility requirements, emphasizes separating and
recycling disaster debris due to limited landfill capacity,
clarifies MEMA's debris-clearance policies and procedures,
provides information regarding air-curtain pit burning
as a means of volume reduction and for the disposal
of animal carcasses, discusses mutual aid agreements,
and more clearly defines the sequence of operations.
This plan
further provides guidance for local communities about
what their responsibilities are during cleanups, and
identifies the responsibilities of state and federal
organizations. It includes sample contracts, an example
mutual aid agreement, an example right-of-entry agreement,
and sample public announcements. It also explains how
to select debris-staging sites, where to find information
on contractors and waste facilities/services, and how
to maximize FEMA reimbursement.
This comprehensive
plan will better prepare the Commonwealth of Massachusetts
and its communities for any future disaster cleanup
efforts. Other states either have or are in the process
of doing this as wellcheck with yours. It could
be a good starting point for preparing your own plan
and can save your staff some time and effort.
So
Are You Ready?
Disaster
debris management is often a component of an overall
emergency management plan but may be a separate document
all together. To get started, here are the key elements
of a specific waste management plan:
- Identify
your project team; include local government agency
personnel for procurement, legal, communications,
operations, and engineering; a debris contractor;
and an oversight engineer.
- Delineate
roles and responsibilities for each team member
and know how to contact them seven days a week, 24
hours a day.
- Understand
local, state, and federal contracting procedures
and be aware of what is and is not eligible for reimbursement.
- Establish
a debris management cycle for normal operations,
increased readiness, response, and recovery.
- Develop
debris classifications, such as vegetative waste,
construction-and-demolition debris, large metals,
and hazardous wastes.
- Determine
appropriate methods for managing each type of debriswhat
can be reduced by grinding or chipping, recycled,
burned, or landfilled.
- Designate
temporary storage/burn sites and develop operating
plans for those sites, including site preparation,
operations, and closeout procedures.
- Document
all decisions, actions, and costs during the response:
this is imperative to receive maximum FEMA reimbursements.
- Set
up a system for reviewing and updating your plan on
a regular basis; if a disaster does hit, record
any lessons learned and revise your plan accordingly.
The main
activities that everyone who has been through this exercise
seemed to emphasize were planning, coordination,
and documentation.
So are you
ready?
Tammy
L. Hayes is a marketing manager specializing in solid
waste at CDM in Tampa, FL.
MSW
- September/October 2004
|