|


This
series of three articles examines the costs involved
in each stage of a generic landfills lifetime,
shows how to do pro forma statements for profit and
loss, and analyzes the tax and financial aspects of
each stage of operation. In so doing, these articles
illustrate the unique profitability of landfill operations
for a given market share. Each article focuses on a
different stage of a landfills operational lifetime.
By
Daniel P. Duffy
Part I examined
a hypothetical landfills market and potential
for waste receipt; as well as its site investigation,
engineering, design, and permitting costs.
This second
article examines the cost of construction for site facilities
and for each landfill cell. Additionally, the operating
cost and disposal volume of each overlapping cell are
described to show how cash flow will change over the
operating life of the landfill.
Part III
will look at the costs of landfill capping and closure,
installation of gas management systems, and post-closure
care and maintenance costs (and how to plan ahead and
provide financial assurance for each).
The Hypothetical
Landfill
As laid out in the previous article, the total
landfill volume would be approximately 4 million cubic
yards. The landfills footprint is square with
dimensions of 1,200 feet, and is a little over 33 acres.
Because of sloping, the final surface grades needing
cap and cover are approximately 34 acres. Similarly,
the bottom of the landfill needing a liner and leachate
system is 33.5 acres. Total acres of landfill construction
(cap and liner) is 67.5, giving a ratio of volume to
construction area of almost 60,000 cubic yards per constructed
acre.
The landfill
is located in an area with a waste disposal market of
approximately $29 million dollars per year at an average
tipping fee of approximately $40 per ton. Assuming that
the landfill gets the bulk of the waste from three counties
in the market area and 10% of the market in the remaining
five counties in the market area, then it can expect
an annual disposal rate of approximately 200,000 tons
per year. At an average tipping fee of $40, its projected
annual gross revenues would be $4.4 million. These revenues
can be expected to increase at roughly the same rate
as the market areas population, approximately
4.5% per year. At 200,000 tons per year, the landfill
will utilize approximately 363,000 cubic yards of airspace
per year. With a total capacity of 4 million cubic yards,
its projected operational lifetime would be 11 years.
During that operating life, the landfill will construct
an average of 3 acres of lined cells and/or final cover
each year.
Landfill
Construction Costs
Up to this point, the landfill operator has completed
(and spent money on) a complete landfill siting and
hydrogeological study. This included a topographic survey
of the site and the establishment of highest stable
groundwater elevation contours. All of this site information
has been graphically represented by site plans and cross
sections. With this data, the landfill designer was
able to complete and obtain approval for a landfill
design that includes a layout of the landfill footprint,
its maximum excavation depths (and its total excavation
volume), location of all of the ancillary site features
and support facilities (scale, access roads, security
fence, parking lot, office trailer, etc.), the maximum
landfill height above existing grades, the location
and extent of surface water runoff, and sedimentation
management controls.
Prior to
any construction, the landfill site will be cleared
and grubbed. Depending on the nature and extent of the
existing vegetation, the costs of clearing and grubbing
can run from $1,000 to $4,000 per acre, with $3,000
being typical. At minimum, those areas that will require
initial construction (the ancillary facilities and structures
areas and the initial waste disposal cell) will require
clearing and grubbing. However, to avoid multiple mobilization
costs for the clearing and grubbing contractor, the
entire site may be cleared and grubbed at once. Subsequent
site maintenance can be performed to prevent the growth
of woody vegetation during the lifetime of the landfill.
Cleared wood can be either hauled offsite or chipped
onsite and stockpiled for future use as mulch.
A site survey
was performed previously (either as a ground survey
or an aerial survey) as part of the hydrogeological
evaluation. During this survey, benchmarks were established,
site features located and topographic contours drawn.
A second site survey is required to stake the various
construction areas of the site. This staking includes
building corners, roadway centerlines, and a grid staking
of the first waste disposal cell. Grids should be laid
out at 50-foot intervals aligned with the limits of
the landfill. Survey stakes should also be set at 50-foot
intervals along slope break lines (crest of slope, toe
of slope, along the center leachate collection pipeline,
etc.). The cost of grade surveying can run from $5,000
to $8,000 per acre, with $7,000 being typical. Additional
survey shots will be taken at these grid points and
break line points through the cell excavation and construction
process, but this is done as part of quality assurance/quality
control, and is done to ensure establishment of proper
slope and grades. The costs of these tasks should be
included in the QA/QC effort.
Once the
site has been surveyed, staked, cleared and grubbed
(and while ancillary facilities and structures are being
built) work can begin on the landfill itself. The first
step is to establish liner construction grades and elevations
by excavation and/or placement of structural fill. Most
landfill construction requires excavation within the
landfill and the use of the excavated soil (if it is
suitable for construction purposes) to construct structural
fill berms around the landfill perimeter. Excavation
in good soil can cost between $2 and $6 per bank cubic
yard. Structural fill soil berms can cost between $6
and $10 per cubic yard.
Exceptionally
stiff subsoils, shale, and rock formations may require
blasting prior to excavation. Though some stiff soil
may be broken up by a dozer ripper attachment, it is
usually more cost-effective to blast. Blasting costs
(drilling, setting charges, explosives, safety requirements)
will be at least an equivalent of an additional $1 per
bank cubic yard, with prices falling for larger volume
excavations.
Conversely,
certain unsuitable soilssuch as peat moss and
other highly organic soilsmust be completely removed
from underneath the landfill, and beyond the landfill
limits if necessary. Such excavation usually costs twice
that of normal soil excavation and will require an equivalent
amount of structural fill soil backfill. This results
in a cost per bank cubic yard of $10 to $22.
For our hypothetical
landfill the maximum average excavation depth is 33
feet. Assuming that blasting is not required and unsuitable
organic soils are not present, the average amount of
excavation per acre is 50,000 to 55,000 cubic yards.
Excavation volumes will be less along the landfill boundary
due to the need for 33% slopes to establish grades,
and will be greatest over the flat floor
of the landfills center. Excavation costs per
acre will run from $100,000 to $330,000 per acre.
The landfill
is assumed to have a minimal structural fill berm constructed
along the landfills perimeter to provide anchoring
for the liner elements and structural toe stability
for the final waste slopes. With 10-foot height and
33% interior and exterior slopes, this berm will require
11 cubic yards of fill soil per linear foot (varying
somewhat with the lay of the land). The total perimeter
of the hypothetical landfill is 4,800 linear feet, resulting
in a berm of approximately 53,000 cubic yards. With
a landfill footprint of 33 acres, the average amount
of perimeter berm constructed per acre would be 1,600
cubic yards. The perimeter berm cost per acre would
be between $10,000 and $16,000. This is just an average
for long-term planning purposes. The landfills
geometry is such that the actual amount of berm required
per acre will vary greatly during construction (acres
adjacent to corner boundaries will require more berm,
acres in the middle of the landfill will require none).
Once the
base grades have been established, the landfills
liner and leachate management system can be constructed.
Most states require only a single liner and leachate
system for municipal solid waste, and require a double
system for hazardous waste landfills only. The lowest
element of the liner/leachate system is the compacted
clay liner. The construction of a clay liner is much
more stringent in terms of material specifications,
construction effort, and quality assurance. The required
in-place density and moisture content will be determined
by Proctor curves and tested by Boutwell test pads to
assure that the maximum allowable permeability is achieved
(usually 1 x 10ee-7 cm/sec). The results of these analyses
and field tests will determine the weight of the compacting
equipment, the penetrating length of the compactors
sheepsfoot pad, the number of passes required to achieve
compacted density, and the field moisture content required
for the construction effort. The cost of a clay liner
runs from $10 to $20 per cubic yard (depending on the
ready availability and quality of the clay). State agencies
require clay liners with a minimum thickness of 2 feet
to 5 feet, resulting in the need for 3,200 cubic yards
to 8,100 cubic yards per acre. The cost per acre of
clay liner construction will vary from $32,000 to $162,000.
A well-chosen landfill site with sufficient good clay
onsite will tend to have lower costs.
After the
clay liner has been constructed and certified, work
can begin on the geosynthetic components of the liner
and leachate management systems. A composite liner system
consists of the clay liner overlain by a high density
polyethylene (HDPE) geomembrane. As with any other plastic,
the cost of geomembrane can vary wildly depending on
the current price of oil. This price may even change
during the course of a single construction season if
a summertime gas shortage increases the price of oil
(yet strangely, the cost of geomembrane never seems
to fall as the result of a sudden gas glut). The thickness
of the geomembrane used in liner systems is typically
60 mils. Smooth geomembrane is used on the flat floors
of the landfills while roughened geomembrane with a
textured surface is used on the 33% side slopes. The
cost of smooth geomembrane can vary from $0.50 per square
foot to $0.75 per square foot. Textured geomembrane
will tend to cost $0.20 per square foot more than the
smooth variety.
The hypothetical
landfill has a total lined area of 33.5 acres divided
into 23 acres of floor and 10.5 acres of slope. An average
lined acre will have approximately 70% smooth geomembrane
and 30% textured membrane resulting in a cost of installed
geomembrane varying from $24,000 to $35,000 per acre.
The actual cost per acre will vary based upon geometry
of the landfill and the location of the cell being constructed.
Some sort
of protective geotextile is installed immediately above
the geomembrane to provide a cushion and minimize impingement
of the liner. This can be either a simple geotextile
or more often a geocomposite drainage blanket. The geocomposite
consists of a factory bonded three-layer sandwich: nonwoven
geotextile bottom cushion, geonet drainage medium, and
a top geotextile filter. It provides both protection
for the underlying geomembrane and more rapid removal
of leachate. The costs of two-sided geocomposites with
8-ounce per square yard nonwoven geotextile layers will
vary as with the geomembranes, with a typical price
range from $0.75 to $1.00 per square foot. The total
cost per acre of geocomposite varies from $33,000 to
$44,000.
Above the
geocomposite is a layer of high permeability granular
material (sand and aggregate). Typically, a minimum
thickness of 2 feet is required, resulting in a total
granular volume of 3,200 cubic yards per acre. The cost
of granular material, like the cost of clay, will vary
wildly depending on local availability and quality.
The cost of granular material can range from $15 to
$20 per cubic yard, resulting in a per acre cost of
$48,000 to $64,000. Often, a geotextile filter blanket
is placed above the granular soil layer, but this is
not recommended.
Installed
within the granular soil layer are the leachate collection
pipes and fittings, gravel pipe mounds, collection sumps,
extraction pumps, force mains and storage tanks. The
pricing of each component is unique, but can be roughly
prorated on a per acre basis.
Assuming
a parallel spacing of 200 feet, each acre will have
approximately 220 linear feet of leachate collection
pipes. With a unit price per foot ranging from $4 to
$8, the cost per acre would be $880 to $1,760.
The amount
of aggregate filter material mounded around and above
the collection pipes to a height of 3 feet will cost
$20 to $25 per linear foot of pipe (this includes any
separation geotextile installed on the aggregate). The
total cost per acre would be between $4,400 and $5,500.
One leachate
collection sump is installed per disposal cell. A typical
cell covers an area of approximately 10 acres. The collection
sump requires intricate welding of the geomembrane,
more extensive QA/QC testing as this is the point where
leachate accumulates, and the installation of large
diameter (18 inches and larger) riser pipes. Total cost
for a sump installation can be about $15,000 to $20,000,
resulting in a pro rated per acre cost of $1,500 to
$2,000.
Each leachate
sump and riser assembly will house extraction pumps,
discharge hoses, pipe fittings, and connections. The
cost of these components will be between $8,000 and
$12,000, resulting in a pro rated per acre cost of $800
to $1,200.
An above-ground
leachate storage tank (5,000-gallon capacity minimum)
will be installed on average for every 100 acres of
landfill. At a cost of $50,000 to $100,000, the pro
rated per acre cost would be $500 to $1,000.
Connecting
the leachate extraction risers to the leachate storage
tanks is a series of double-walled (minimum 4-inch interior
diameter) HDPE force mains. The cost of trenching, pipe,
installation, bedding, and backfill can range between
$20 and $25 per linear foot. Assuming one pipeline per
storage tank (or per 100 acres of landfill area) and
a distance of 1,000 linear feet, the pro rated cost
of the force main would be $200 to $250 per acre.
The total
cost per acre of the leachate management system would
be between $8,000 and $12,000 (approximately).
In addition
to the physical acts of construction and installation,
management and quality oversight is required. This is
typically done by independent third-party consultants
and breaks down as follows:
- Geomembrane
liner construction management costs from $18,000 to
$20,000 per acre.
- Clay liner construction management costs from $2,000
to $4,000 per acre.
- Overall project management costs from $12,000 to $16,000
per acre.
- Construction surveying and drawings costs from $6,000
to $10,000 per acre.
- Earthwork (structural fill and excavation) QA/QC costs
from $15,000 to $20,000 per acre.
- Liner (clay and geomembrane) QA/QC costs from $16,000
to $20,000 per acre.
- Leachate management system installation QA/QC costs
from $6,000 to $9,000 per acre.
Total overhead
and quality control would therefore range from $75,000
to $100,000 per acre.
Table 1 summarizes
the above initial construction costs and the typical
cost per acre of landfill construction.
| Table 1. Typical Construction Costs |
| Clear and Grub |
$ |
1,000 |
$ |
3,000 |
| Site Survey |
|
5,000 |
|
8,000 |
| Excavation |
|
100,000 |
|
330,000 |
| Perimeter Berm |
|
10,000 |
|
16,000 |
| Clay Liner |
|
32,000 |
|
162,000 |
| Geomembrane |
|
24,000 |
|
35,000 |
| Geocomposite |
|
33,000 |
|
44,000 |
| Granular Soil |
|
48,000 |
|
64,000 |
| Leachate System |
|
8,000 |
|
1002,000 |
| QA/QC |
|
75,000 |
|
100,000 |
| TOTAL |
|
$336,000 |
|
$774,000 |
The cost of constructing a landfill can range from $300,000
to $800,000 per acre, with the main cost difference
due to availability of clay and ease of excavation.
For the purposes of this study, the hypothetical landfill
will be assumed to be well sited with ample clay and
easy excavation. Its cost of construction per acre will
be approximately $350,000. Support
Facilities Construction Costs
Typically all of the ancillary structures and facilities
(with the possible exception of the access roads) are
constructed up front. Assuming a square landfill footprint
of 1,200 feet by 1,200 feet, the landfills perimeter
access road would have a length of approximately 1,250
along each side for a total of 5,000 feet. Given the
possible setbacks from the property line required by
the state regulatory agency, and the area required for
other facilities, the security fence could be approximately
6,000 feet. Cost for support facilities and structures
are summarized as follows:
- Each
buildings cost will depend on its function and
may vary as much as $10 to $100 per square foot. Office
buildings will cost between $60 and $100 per square
foot, maintenance buildings between $50 and $70 per
square foot, with shacks and tool sheds closer to
$10 to $20 per square foot. Assuming 10,000 square
feet of maintenance and 3,000 square feet of office
space, the cost of onsite buildings will range from
$680,000 to $1 million.
- Fencing
costs between $10 and $20 per linear foot with gates
costing between $1,000 and $2,000 per linear foot.
Signage placed along the fence (usually at 200-foot
intervals) will cost between $10 and $20 each. Total
security barrier costs would range from $65,000 to
$130,000.
- Modular
truck scales and associated computer systems can cost
between $100,000 and $150,000 each (one per landfill)
- Wheel
wash facilities can cost between $200,000 and $250,000
(one per landfill).
- Gravel
roads cost between $1 and $2 per square foot while
asphalt roads cost between $6 and $9 per square foot.
Assume only gravel roads and parking lots are constructed
with a 24-foot width at 5,000 linear feet. The total
access road costs would range from $120,000 to $240,000.
- Total
support facility and ancillary structure costs would
range from $1.165 million to $1.77 million. Given
its size, it is assumed that the hypothetical landfill
will need minimal support facilities and is located
so as to minimize costs at $1.2 million.
Disposal
Fees and Operations Costs
As previously stated, the landfill is in a market
area with an average tipping fee of $40 per ton. Each
landfill acre will have an average disposal capacity
of 60,000 cubic yards. At an average in-place density
of 0.55 tons per cubic yard, this is equivalent to 33,000
tons per cubic yard. Therefore, each acre has a gross
profit potential of $1.32 million (though this will
vary significantly during the lifetime of the landfill
since some cells will be able to place waste in masses
that overlay the slopes of previous waste disposal cells).
The entire 33-acre landfill has a gross profit potential
of approximately $43.5 million.
By comparison
the 33.5 acres of liner construction will cost $11.725
million. With the support facilities and structures,
the total capital costs prior to final closure would
be approximately $13 million.
Operating
costs involve staffing, utilities, equipment operations
(leasing or loan payments, fuel, oil, lubricants, maintenance,
etc.), leachate disposal and treatment, scale operations,
paperwork, recordkeeping, billings, engineering staff
and services, environmental monitoring, and daily cover
applications. Equipment is the single largest operating
cost closely followed by daily cover.
At 200,000
tons per year, the average daily waste receipt would
be between 500 and 600 tons (a relatively large amount
by real world standards). At minimum, this landfill
would require
- A front
end loader for onsite hauling of bulk material and
small construction tasks (CAT 950 or equivalent).
- A dozer
(CAT D7 or D8) equipped with a trash rack to spread
dirt and waste.
- A steel,
wheeled compactor (CAT 826G or equivalent) to compact
the waste and achieve maximum possible in-place density.
- Additional
equipment such as water spray trucks (to hold down
dust), scraper, backhoe, several pickup trucks, and
a road grader.
The total
unit cost of operations is relatively small compared
to the landfills capital costs. This makes landfill
economics unique among industrial or construction operations
(a landfill is both). As a percentage of the tipping
fee, operating costs can run from 5% to 15%. Larger
landfills will have a smaller percentage. Table 2 provides
a summary of typical annual operating costs.
| Table 2. Typical Operating Costs |
| Operations (equipment, staff, facilities and general maintenance) |
$500,000 |
| Leachate Collection and Treatment (assumes sewer connection and discharge cost of $0.02/gal.) |
$10,000 |
| Environmental Sampling and Monitoring (groundwater, surface water, air gas , leachate) |
$30,000 |
| Engineering Services (consulting firms and in-house staff) |
$60,000 |
| This is equivalent to $3 per ton, or 7.5% of the tipping fee |
Determining
Cash Flow
The cost of the support facilities and ancillary
structures is incurred prior to the start of landfill
operations, in Year 0, $1.2 million. The first three
acres of lined cells will also be constructed in Year
0 at a cost of $350,000 per acre, or $1.05 million.
The total costs incurred in Year 0 would therefore be
$1.55 million. On average,
each year will require the construction of another 3
acres at a cost of $1.05 million. However, larger areas
may be constructed at greater intervals, such as 9 acres
every 3 years. Annual operating costs will be $600,000
for a total average annual cost of $1.65 million.
Each year,
the site receives 200,000 tons and charges a tipping
fee of $40 per ton. This results in annual gross revenues
of $8 million. This results in an annual net
profit (before interest and taxes) of $6.35 million.
Assuming that no final cover is constructed during the
first year of operations, the payback period for the
initial start-up costs in Year 0 is about 3 to 3 months.
However, this does not include annual costs for partial
installation of final cover or disbursements to a sinking
fund to cover the costs of the 30-year post-closure
care.
Daniel
P. Duffy, P.E., is an environmental engineer in Cincinnati,
OH.
MSW
- July/August 2005
|