|


DCs
Benning Road site adds much-needed space, streamlined
approach in $8 million expansion.
By
Larry Trojak
It seems
almost inconceivable that, in 2005, our nations
capital would still be making wholesale changes to its
waste transfer program. We tend to assume that, since
our governing bodies reside there, change would emanate
from this city and wethe rest of the countrywould
be simply following its lead. Such, however, is not
the case. In fact, because of difficulty meeting EPA
regulations, only in the last 10 years has the city
stopped incinerating its MSW. However, while change
in Washington may not be quick in coming about, when
it does, its significant, a fact borne out in
the ongoing $8 million expansion of the citys
Benning Road Transfer Station. When complete, the upgraded
site, which once struggled to handle 500 tpd of waste,
will be capable of transferring as much as 2,500 tpd.
Much of the tipping floor and loading area will be fully
enclosed and a trio of new Builtrite Model 2100 Material
Handlers from Northshore Mfg. will be at work maximizing
trailer volumes as they leave the site.
In Need
of a Change
Waste transfer is an unfortunate fact of life in
the Washington metro area, according to Ronald Marshall,
facility manager at the Benning Road site.
Theres
simply no other option for us in this area, he
says. The DC area generates better than 4,000
tons of MSW each day, and every bit of it has to be
removed by truck from the area. About half that volume
goes to the Energy/Resource Recovery Facility in nearby
Fairfax County [Virginia], but the remainder gets landfilled
and the nearest fill, the King George Landfill, is 76
miles away in Fredericksburg, Virginia. Other loads
are hauled 130 miles and 140 miles to the Charles City
and Middle Peninsula landfills, respectively. The bottom
line is an efficient transfer station system is key
for the District.
Building
Blocks
Until recently, trucks coming into the Benning
Road site would dump their loads into a pit and then
cranes would pick them up out of the pit and load them
onto a conveyor, which fed it into the truck. It was
a very slow and cumbersome process that needed upgrading
badly. Initial expansion work was started in February
2004, and according to Adedeji Fawole, senior project
engineer for Columbia, MDbased SCS Engineers,
the design team hired by general contractor Keystone
Plus, it had its own set of challenges from the outset.
Even
in the design phase, we were faced with a number of
challenges, he says. The north and east
sides of the site are bordered by undeveloped park land
owned and operated by the US Parks Service. On the south
side is the massive Pepco power plant and there are
parking areas throughout that could not be blocked or
eliminated. So getting the expansion to fit in a relatively
small areayet keep trucks flowing in and out in
an efficient mannertook some careful and creative
design.
Fawole adds
that the expansion was further complicated by the fact
that the transfer station is situated on what was once
a landfill itself.
To
ensure stability, we had to drive steel H-piles down
60 feet to bedrock. Once we had those piles in place,
we were set to start the build. Keep in mind that the
site will remain open all throughout the construction
process, with trucks coming in and leaving, so that
adds another element of challenge to the project. When
it is complete, the entire tipping floor and push-pit
area will be covered and enclosed, making the working
environment much better, particularly in rainy or snowy
weather.
Phasing
In, Loading Out
The sites expansion10,000 feet of additional
work areais taking place in phases, with the first
phase being the construction and implementation of the
new loading areaone of three that will eventually
serve the Benning Road site. That first loading area
became operational in December 2004.
We
are using Builtrite Model 2100 Material Handlers at
each load-out station to tamp, sort, and occasionally
pick material that has been pushed into a trailer waiting
on a loading ramp below the tipping floor, says
Marshall. This is far more efficient than anything
else we have done in the past. Each handler has a reach
of about 27 feet, more than enough to access areas around
the load-out opening as well as all corners of the trailer
being loaded. And, because the loader cabs are heated
and air conditioned, the operators will have a comfortable
working environment throughout the year.
Tamping the
loads, one of the primary functions of the loaders,
eliminates voids, which maximizes volumes, says Sylvestre
Yorrick, chief of the Department of Public Works
Disposal Division. Each trailer is rated for an
80,000-pound load and we want to ensure we get that,
considering the distances the trucks have to travel.
The waste, particularly when it is right off the tipping
floor, is fluffy and needs to be densified.
To make that
happen, each Builtrite Handler is equipped with a flat-bottom
grapple, specially sized for the Benning Road operation.
We initially mounted our standard 27-inch grapples
on those loaders, says John Anderson, Northshore
Mfg.s president. However, due to the size
and configuration of the load-out area, they seemed
too large. We were able to specially design and build
a 19-inch version of that same grapple for the DC site
and it has made a real difference for the operators.
Role Reversal
When fully operational, the Benning Road Transfer
Station will essentially be changing roles with its
counterpart, the Fort Totten Transfer Station, located
about 10 miles away, says Yorrick.
Fort
Totten currently does about 1,500 tons per day and we
do 500 tons per day here, he says. In March
of this year, when our expansion is complete, we will
be handling the 2,000 tons per day and Fort Totten will
be cut back dramatically. At that time, it will undergo
an almost identical expansion to what we are doing here.
Because each
transfer stations location best serves haulers
from different parts of the DC metro areaFort
Totten, the citys west side; Benning Road, the
east sidethe Solid Waste Department needs both
sites fully operational and knows it can keep both busy.
The
volumes of waste for this area are forecast to increase
in the coming years, particularly after the closing
of several improperly zoned private transfer stations
located within the city limits, says Yorrick.
When that happens and both expansions are complete,
we are forecast to be handling as much as 2,500 tons
per day at each site. We are confident that streamlining
the transfer processboth through the addition
of the loading stations and the use of the Builtrite
Handlers to maximize load densitieswill help offset
the cost of the projects by dramatically improving the
efficiencies of both sites.
Larry
Trojak is principal in Trojak Communications at Ham
Lake, MN.
MSW
- July/August 2005
|